A Planned External Cleaning Programme for Commercial Buildings

Build an annual external cleaning programme for a commercial building: what to include, a sample 12-month calendar, contract terms, KPIs and how to budget.

Quick answer: A planned programme fixes what gets cleaned, how often and how it's recorded for a year or more, instead of booking cleans when the building starts looking tired. A good one covers glass (frequent), frames and cladding (6–12 monthly), stone and render (as needed), gutters (annual), plus a condition check on every visit. It sets fixed visit dates, weather rules, reporting and KPIs. The usual results are a lower cost per visit, cleaning records that keep warranties valid, and defects caught early.

Sample 12-month programme (mid-size London office)

MonthActivity
JanGlass & entrance clean (all elevations)
Feb—
MarGlass clean; post-winter condition check
AprCladding & frames wash (neutral detergent); bird-proofing check
MayGlass clean
Jun—
JulGlass clean
Aug—
SepGlass clean; sealant visual check; book any repairs before winter
OctCladding & frames wash; anchor inspection (if due)
NovGutter & outlet clearance after leaf fall
DecGlass & entrance clean (pre-holiday presentation)

Entrances and shopfronts are cleaned more often, typically weekly or fortnightly at ground level. Stone and render deep cleans (every 5–10 and 1–3 years respectively) are scheduled into the long-term plan. See how often to clean commercial façades.

What to put in the contract

  • Scope per visit: elevations, elements (glass only, or glass + frames + cladding) and levels.
  • Methods and products, including any restrictions from cladding or coating warranties.
  • Visit dates and weather rules: who reschedules, and whether weather days are charged.
  • Access: anchors in date (BS 7883) or BMU examined (LOLER). Who arranges and pays for the tests?
  • Reporting: dated before and after photos, a defect log, and same-day notice of urgent issues.
  • Complaints: a re-clean window, e.g. within 5 working days.
  • Price: per visit or annual, with a review date.

KPIs worth tracking

KPITarget example
Visits completed on schedule≥ 95% (weather excepted)
Reports deliveredWithin 3 working days of each visit
Defects reported per visitLogged, with photos
Re-clean requests< 5% of visits
Safety incidentsZero

Budgeting

A planned programme usually costs less per visit than ad-hoc booking, because mobilisation and planning are spread over the year and the contractor can schedule efficiently. As a market guide, published UK figures suggest a 12-storey London office budgets around £4,000–£6,000 a year for quarterly façade cleaning. Larger and more complex buildings cost more.

FAQ

Can I start a programme part-way through the year?

Yes. The first visit usually includes a baseline condition check and a deeper clean.

Is a planned programme a long contract?

Typically 12 months with a renewal option. Some clients prefer 2–3 years to lock in pricing.

Does the programme cover repairs?

Usually not, but defects found are reported and can be quoted separately, often for the next scheduled visit.

Get a programme proposal

See our façade cleaning and building maintenance, or request a site survey.

Sources

  • Pure Seal Services, How often should windows be cleaned?: London budget example.
  • BS 7883:2019; LOLER 1998.
Keep reading

More guides

When Is Rope Access the Right Choice for High-Level Building Work?

Is rope access right for your job? A task-by-task guide to what it does well, where it struggles and when scaffold or a MEWP is better.

Read the guide →

When Should a Building's Anchor Provision Be Reviewed?

Beyond the annual BS 7883 inspection, seven situations mean your roof anchors need reviewing, such as refurbishment, new plant and missing records.

Read the guide →

When Cleaning Is Not Enough: Signs a Façade Needs Repair

A façade clean often uncovers defects the dirt was hiding: cracks, open joints, failed sealant, rust and spalling. What each means and what to do next.

Read the guide →
Planning work at height?

Need help with your building? Talk to our team.