Quick answer: A good scope of works answers seven questions: where (exact elevations, levels, drops), what (the problem and the required outcome), how much (quantities or a measured allowance), to what standard (products, manufacturer instructions, relevant British Standards), when and under what constraints (hours, tenants, entrances), what's excluded, and what you get at the end (photos, report, warranty). Write it that way and every contractor prices the same job, so you can compare quotes properly.
The template
| Section | What to write | Example |
|---|---|---|
| 1. Location | Address, elevations, levels, gridlines or marked-up photos | "East and south elevations, levels 3–9, see marked photos A–F" |
| 2. Background | The problem and its history | "Leaks at window heads on L5–L7 in wind-driven rain since 2025" |
| 3. Required outcome | What "done" looks like | "Watertight perimeter seals; water-tested on 3 sample windows" |
| 4. Tasks | Each task, in order | "Cut out existing perimeter sealant; prepare; prime; backer rod; re-seal" |
| 5. Quantities | Measured, or a provisional allowance | "Approx. 240 linear metres; contractor to verify" |
| 6. Standards & products | Product or performance spec, manufacturer data, BS references | "Low-modulus silicone suitable for the substrate, to manufacturer's instructions; selection guided by BS 6213" |
| 7. Constraints | Hours, access, tenants, events, permits | "Work 07:00–18:00; main entrance must stay open; roof permit required" |
| 8. Information provided | What you're giving bidders | "Anchor certificate (May 2026), asbestos register extract, O&M sealant data" |
| 9. Exclusions | What isn't included | "Internal making good; replacement glass" |
| 10. Provisional items | Unknowns with a rate | "Additional defects found: day rate + materials, by agreement" |
| 11. Deliverables | What you receive | "Before/after photos per drop; completion report; 5-year workmanship warranty" |
| 12. Programme | Dates or a window | "Complete by 30 March; weather contingency of 3 days" |
Common mistakes that cause bad quotes
- Describing the fix, not the problem. "Re-seal window 5.12" may not fix a leak entering at the coping. Describe the symptom too.
- No quantities. Without them, bidders guess, and the cheapest guess wins.
- No deliverables. One bid includes a report and one doesn't, so they aren't comparable.
- No provision for unknowns. Every façade hides something. Agree a variation rate up front.
- Copying a generic spec that doesn't match the building's materials.
When a contractor-written scope is fine, and when it isn't
For routine maintenance (cleaning, gutters, small repairs), a reputable contractor can write the scope after a survey, and you then check it against this template.
For larger or technical work (leaks with an unclear cause, repairs to a curtain wall system, listed buildings, anything that counts as construction work under CDM 2015), get an independent building surveyor or façade consultant to write or check the specification.
FAQ
Who should write the scope of works?
For small, routine jobs, the facilities manager with contractor input. For technical or high-value work, a building surveyor or façade engineer.
Should the scope name products?
Either name a product, or state the performance needed and require the contractor to propose a compatible product with data sheets.
How detailed should quantities be?
As accurate as you can make them. Where they're uncertain, state that they're approximate and ask bidders to verify them on survey.
Get help scoping
We'll survey and write a scope you can use to compare us fairly with other bidders. See our building maintenance and roof repairs, or request a site survey.
Sources
- BS 6213:2000+A1:2010, Selection of construction sealants: guide.
- CDM Regulations 2015.
- RICS, New Rules of Measurement: NRM 3 (order of cost estimating for building maintenance works).