Quick answer: A rope access site survey usually takes from about an hour for a straightforward job to longer for a large or complex building. The surveyor looks at the work areas (often from the ground, the roof and inside), the roof anchorage and access route, the ground-level areas that will need an exclusion zone, and any site constraints such as entrances, tenants and loading bays. After the visit you should receive a fixed quote, the method and an outline programme, followed by full RAMS before work starts.
Before the survey: what to have ready
- Roof access: keys, codes, lift access, and someone who knows the route.
- The last anchor inspection certificate. BS 7883 recommends anchors are inspected at least every 12 months.
- Drawings or elevations if you have them, plus any previous reports.
- Photos of the problem, and leak diary dates if it's a leak.
- Constraints: working hours, events, deliveries and sensitive tenants.
- Asbestos information if the work touches the building fabric, from the asbestos register for the building.
What the surveyor checks, step by step
1. The brief (5–10 minutes)
A conversation about what you need, what's driving it (a leak, an appearance issue, a lease requirement, an insurance requirement), deadlines, and what you want at the end.
2. The work areas
The surveyor views each elevation and identifies the drops needed. A drop is one vertical run from roof to ground, and the number of drops is the biggest single factor in time and cost. They photograph defects and note materials, such as glass, aluminium, stone or render, because these decide methods and products.
3. The roof
- Anchorage: permanent anchors, davits, eyebolts or suitable structure. Are they marked, tested and in date?
- Edge conditions: parapet height, copings that could be damaged by ropes, fragile roof areas.
- Access route: hatches, ladders, plant areas and how equipment will get up.
- Hazards: plant, flues, aerials, fragile rooflights, and any restricted areas such as roof-mounted telecoms equipment.
4. Ground level
- Where exclusion zones go below each drop, and how pedestrians will be diverted.
- Entrances, fire exits, bus stops, loading bays and whether work must be timed around them.
- Whether any part of the work affects the public highway.
5. Inside (if relevant)
For leaks, the surveyor checks where water appears inside. For window work, they check whether windows open and whether internal access is needed.
What you receive afterwards
| Document | What it contains | When |
|---|---|---|
| Quote | Scope, number of drops, inclusions and exclusions, programme, price | After the survey, once the scope is agreed |
| Method summary | Access method and why it was chosen | With the quote |
| RAMS | Job-specific risk assessment, method statement, rescue plan, exclusion zones | Before work starts |
| Programme | Dates, hours, weather contingency | Agreed when booking |
Surveys that save money
A good survey often reduces the price, because it:
- groups work to reduce the number of drops;
- combines tasks, such as cleaning and a defect check, into one visit;
- finds out early whether anchors need testing, so it doesn't delay the job;
- avoids variations caused by unknowns.
FAQ
Is the site survey free?
Ask when you book. Any charge for a survey should be confirmed before the visit.
Do I need to be there?
Someone needs to provide roof access and explain the brief. A facilities team member or site manager is ideal.
Can you quote without a survey?
Simple jobs can be priced from photos with stated assumptions. Anything involving leaks, defects, multiple elevations or unknown anchorage should be surveyed.
Will the surveyor go on ropes?
Not usually. Most surveys are visual from the roof and ground. A short rope inspection can be arranged if close access is needed to scope repairs.
Book a survey
Send the address and a few photos and we'll arrange a time. See our rope access in London and services, or request a site survey.
Sources
- BS 7883:2019 (anchor inspection).
- Control of Asbestos Regulations 2012 (duty to manage).
- Work at Height Regulations 2005.