A practical pre-work checklist for facilities managers commissioning high-level maintenance: documents, anchors, asbestos, RAMS, permits and tenants.

Quick answer: Before any contractor works at height on your building, you should have: a clear scope, the contractor's competence and insurance evidence, job-specific RAMS with a rescue plan, in-date anchor or BMU certificates, asbestos information for the work areas, a permit to work (if your site uses them), tenant notices, and an agreed sign-off and reporting format. The checklist below covers all of it.

The checklist

A. Scope (2–4 weeks before)

  • Areas, elevations and drops identified, ideally marked on photos or drawings
  • Task described as the problem ("water ingress at level 5, east elevation") as well as the hoped-for fix
  • Deliverables agreed: photos, report, defect list, warranty
  • CDM 2015 status checked. If it's construction work, you have client duties, including providing pre-construction information.

B. Contractor competence

  • IRATA certificates (or other relevant competence) for named operatives, and a named Level 3 supervisor for rope access
  • Employer's liability (legal minimum £5m) and public liability certificates in date
  • Accreditation (e.g. CHAS, SafeContractor, Constructionline) if your policy requires it
  • References for similar work

C. Building information you must provide

  • Anchor or BMU certificates: anchors inspected within the last 12 months (BS 7883), and BMUs thoroughly examined under LOLER (typically every 6 months)
  • Asbestos register extract for any area where the fabric will be disturbed (Control of Asbestos Regulations 2012)
  • Roof hazards: fragile rooflights, plant, restricted telecoms areas
  • Drawings and previous reports, if available

D. Safety documents

  • RAMS specific to your building, naming drops, anchors, exclusion zones and weather limits
  • Rescue plan showing how the team recovers a casualty without relying on emergency services
  • Exclusion zones and pedestrian routes agreed
  • Permit to work issued (roof access, hot works if any)

E. Occupiers

  • Tenant notice sent 1–2 weeks before
  • Reception, security and cleaning teams briefed
  • Sensitive areas and times identified (events, deliveries, quiet hours)

F. On the day

  • Pre-start meeting with the Level 3
  • Sign-in and induction
  • Exclusion zones checked before work starts
  • Contact number for the supervisor

G. After

  • Walk-round or photo sign-off of completed work
  • Report and defect list received
  • Records filed (O&M, maintenance log, warranty)
  • Permit closed

Good detail vs unhelpful detail in a brief

UnhelpfulHelpful
"Fix the leak""Water through window head, level 5 east, only in south-westerly rain since March. Photos attached."
"Clean the building""Clean all glass and frames, north and east elevations, levels 1–9. Cladding excluded."
"Check the façade""Close inspection of stone copings and parapets on all elevations, with a photo-referenced defect report."

FAQ

Is the facilities manager responsible for contractor safety?

The contractor is responsible for how it carries out the work. As the client or person in control of the premises, you're responsible for appointing competent contractors, providing information about the building, and coordinating with occupiers. Under CDM 2015, clients of construction work have specific duties.

Do we need a permit to work for rope access?

The law doesn't require one specifically, but many buildings use permits to control roof access. If yours does, issue one.

How long should RAMS take to get?

A competent contractor can usually issue job-specific RAMS within a few working days of the survey.

Make it easy

We'll send our RAMS, certificates and insurance with every quote. See our building maintenance and services, or request a site survey. Related: how to choose a rope access contractor.

Sources

Keep reading

More guides

When Is Rope Access the Right Choice for High-Level Building Work?

Is rope access right for your job? A task-by-task guide to what it does well, where it struggles and when scaffold or a MEWP is better.

Read the guide →

When Should a Building's Anchor Provision Be Reviewed?

Beyond the annual BS 7883 inspection, seven situations mean your roof anchors need reviewing, such as refurbishment, new plant and missing records.

Read the guide →

When Cleaning Is Not Enough: Signs a Façade Needs Repair

A façade clean often uncovers defects the dirt was hiding: cracks, open joints, failed sealant, rust and spalling. What each means and what to do next.

Read the guide →
Planning work at height?

Need help with your building? Talk to our team.