Quick answer: A high-level sign replacement can usually be done without closing the building if it's planned in this order: (1) consent (advertisement consent if size, position or illumination changes), (2) survey of the existing fixings, structure and power, (3) electrical isolation plan with a qualified electrician, (4) lifting plan for removal and installation (rope access for lighter elements; hoist, MEWP or crane for heavy ones), (5) public protection with exclusion zones and out-of-hours work at entrances, and (6) make-good and handover: sealing old fixing holes, testing, and records.
Step-by-step plan
1. Consent and design (4–12 weeks before)
- Advertisement consent may be needed for new or changed signs, particularly illuminated signs, larger signs, and those on listed buildings or in conservation areas.
- Get structural confirmation that the building can carry the new sign's weight and wind load.
- Confirm power supply and controls with the electrician.
2. Survey (2–4 weeks before)
- Existing fixings, brackets and what's behind them.
- Access routes and anchors (in date: BS 7883).
- Weight of the old and new sign and their components.
- Ground-level constraints: entrances, pavement, traffic.
3. Access and lifting
| Sign element | Typical method |
|---|---|
| Individual letters, light panels, small modules | Rope access with hand-lifting and haul systems |
| Medium panels | Rope access with a planned hoist or MEWP |
| Large, heavy signs or structures | MEWP or crane, with rope access for fixing and detail |
Lifting operations need planning under LOLER 1998, and for complex lifts, a lift plan by a competent person.
4. Electrical isolation
- Isolate and lock off before removal (Electricity at Work Regulations 1989).
- Reconnection and testing by a qualified electrician to BS 7671, with certification.
5. Keeping the site open
- Out-of-hours work over entrances: early mornings, evenings, weekends.
- Exclusion zones and ground staff; covered walkways if needed.
- Tenant and staff notices.
- Coordinate with council if the highway is affected (crane or MEWP on the road).
6. Make-good and handover
- Seal and make good old fixing holes to prevent water ingress.
- Clean the area behind the old sign, which often reveals staining or defects.
- Handover pack: electrical certificate, fixing details, photos, maintenance guidance.
FAQ
How long does a signage replacement take?
Small letter sets can take a day or two. Large illuminated signs with crane lifts are planned around consent, lifting and electrical work.
Can it be done at night?
Often, yes, especially over entrances, subject to noise rules and lighting.
What happens to old fixing holes?
They should be sealed and made good. Left open, they're a common source of water ingress.
Plan your replacement
See our rope access in London and services, or request a site survey. Related: maintaining high-level signage and LED systems.
Sources
- Town and Country Planning (Control of Advertisements) (England) Regulations 2007.
- LOLER 1998; Electricity at Work Regulations 1989; BS 7671.
- BS 7883:2019.