Quick answer: Prioritise external defects in this order: (1) anything that could fall or injure someone, (2) active water ingress, (3) defects that will get rapidly worse or more expensive if left (e.g. corroding fixings, failing sealant before winter), (4) issues affecting operations, tenants or compliance, then (5) appearance. Score each defect on likelihood × consequence, group fixes by location so each access visit covers as much as possible, and re-inspect anything you defer.
A simple scoring matrix
Score each defect from 1 to 5 for consequence and for likelihood, then multiply.
| Consequence (C) | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Cosmetic | Minor deterioration | Water ingress / tenant impact | Significant damage / business disruption | Injury to people |
| Likelihood (L) | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Rare | Unlikely in 2 years | Possible in 1–2 years | Likely within a year | Imminent / already happening |
Priority = C × L
| Score | Priority | Action |
|---|---|---|
| 15–25 | 🔴 P1: Immediate | Make safe now (cordon, remove, secure); repair within days or weeks |
| 8–14 | 🟠 P2: Short term | Repair within 3–6 months, before winter if relevant |
| 4–7 | 🟡 P3: Planned | Budget for 1–2 years; group with other work |
| 1–3 | ⚪ P4: Monitor | Re-check at the next inspection |
Worked examples
| Defect | C | L | Score | Priority |
|---|---|---|---|---|
| Loose stone fragment above main entrance | 5 | 5 | 25 | 🔴 P1 |
| Active leak into tenant office, L6 | 4 | 5 | 20 | 🔴 P1 |
| Failed perimeter sealant, west elevation, before winter | 3 | 4 | 12 | 🟠 P2 |
| Rust staining at stone cramps, no movement yet | 4 | 2 | 8 | 🟠 P2 (investigate) |
| Algae on north render | 2 | 3 | 6 | 🟡 P3 |
| Faded paint on stairwell tower | 1 | 3 | 3 | ⚪ P4 |
Three mistakes to avoid
- Prioritising by visibility. The most visible defect (dirty glass) is rarely the most important one (a corroding cramp hidden behind a cornice).
- Fixing defects one by one. Each access visit costs money. Group P2 and P3 items by elevation and drop so one mobilisation handles several.
- Deferring without a date. Every deferred item needs a re-inspection date and an owner.
Turn it into a register
| Ref | Location | Defect | C | L | Score | Priority | Action | Owner | Due |
|---|
A register like this makes budget conversations with owners much easier, and shows a defensible, risk-based approach if anything is ever questioned.
FAQ
Who decides the priority?
The facilities or asset manager, informed by the inspector's findings. Engineers should rate anything structural.
Should every P1 be repaired immediately?
Every P1 should be made safe immediately. The permanent repair can follow quickly once it's planned.
How do I justify the budget?
Present the register with scores, photos and grouped costs. Showing what's P1 and what's deferrable makes the conversation evidence-based.
Get your defects prioritised
See our building maintenance and roof repairs, or request a site survey. Related: what should be in a high-level condition report.
Sources
- HSE, Risk assessment: a brief guide to controlling risks in the workplace (INDG163): likelihood × consequence approach.
- BS 8210:2020 (facilities maintenance management).