Quick answer: Most premature paint failures, such as peeling, flaking, blistering and early discolouration, come from poor preparation, not poor paint. Proper prep means cleaning (dirt, chalk, algae, salts), removing loose and failed coatings, repairing the substrate (cracks, spalls, rust), making sure the surface is dry, checking compatibility and adhesion, and priming correctly. It often takes as long as, or longer than, the painting itself, and it's the first place cheap quotes cut corners.
Preparation by substrate
| Substrate | Key prep steps | Common failure if skipped |
|---|---|---|
| Render & masonry | Clean; biocide on algae; remove loose and flaking paint; fill cracks; allow to dry; stabilising primer on chalky or powdery surfaces | Peeling, algae coming back through, blistering from trapped moisture |
| Previously painted surfaces | Wash; remove loose paint; check adhesion; key glossy surfaces; check compatibility (e.g. masonry paint over silicate) | Flaking of the new coat |
| Steel / iron | Remove rust to the specified standard; prime with rust-inhibiting primer quickly | Rust bleeding and blistering within months |
| Galvanised steel | Degrease; abrade or etch; specialist primer | New paint peeling off in sheets |
| Aluminium | Degrease; abrade; suitable primer | Poor adhesion |
| Timber | Remove failed paint; treat rot; fill; knot; prime bare wood; check moisture | Flaking, rot under the paint |
Tests that show a surface is ready
- Moisture: use a moisture meter on masonry, render and timber. Painting damp substrates traps water.
- Dew point: the surface should be at least 3 °C above dew point (ISO 8502-4), otherwise condensation forms under the paint.
- Adhesion of existing coatings: a cross-cut or tape test (e.g. ISO 2409) on old paint. If it fails, the old paint must come off.
- Chalking: rub with a dark cloth. Heavy chalking needs washing and a stabilising primer.
- Salts/efflorescence: brush off and let the substrate dry out before coating.
- Lead: test old paint on pre-1960s buildings before sanding or scraping (Control of Lead at Work Regulations 2002).
Shortcuts to watch for in quotes
- "Wash down and two coats", with no mention of removing failed paint or repairs.
- No primer specified on bare, chalky or metal surfaces.
- No moisture or adhesion checks.
- Products mixed across manufacturers without checking compatibility.
- Winter start with no weather conditions stated.
Agree hold points
Ask to inspect or receive photos at three stages: after prep, after priming, and on completion. It's the simplest way to make sure prep isn't skipped on areas you can't see, which on a high-level job is most of them.
FAQ
How long should surface prep take?
It varies with condition. On a weathered façade, prep can be half or more of the total time.
Can you paint over algae?
No. It must be killed and removed with a biocide first, or it will grow back through the paint.
Does new paint need a primer on previously painted render?
If the old coating is sound and compatible, often not. If it's chalky, patched or bare in places, a stabilising primer is usually required. Follow the manufacturer's system.
Get it prepared properly
See our external painting and building maintenance, or request a site survey. Related: external painting at height: what to specify.