Quick answer: RAMS stands for risk assessment and method statement. The risk assessment identifies what could go wrong on your building and what will be done to prevent it. The method statement describes, step by step, how the work will be carried out. A good RAMS is specific to your building and the job, written before work starts, shared with you for review, and briefed to every person on the team. A generic document with your building's name pasted into it is a red flag.
Why RAMS matters to you
Work at height is one of the most closely regulated activities in the UK. Employers must assess the risks of their work under the Management of Health and Safety at Work Regulations 1999, and work at height must be planned, supervised and carried out by competent people under the Work at Height Regulations 2005. On building maintenance and repair, the Construction (Design and Management) Regulations 2015 may also apply, with duties for clients as well as contractors. Take advice on how these apply to you.
For you as the building manager, the RAMS is the practical evidence that the contractor has thought about your building. It also tells you what the contractor expects from you.
The two documents
| Risk assessment | Method statement | |
|---|---|---|
| Question it answers | What could go wrong, who could be harmed, and how do we prevent it? | How will we do the job, in what order, and with what equipment? |
| Format | Hazards, who is at risk, existing controls, additional controls, a risk rating | A step-by-step sequence of the work |
| Focus | Danger | Process |
They are usually combined into one pack, with the method statement referring to the controls identified in the risk assessment.
What a good risk assessment contains
- Hazards specific to your building: roof edges, fragile areas, plant, live equipment, glazing, power lines and wind exposure
- Who could be harmed: technicians, occupants, the public, neighbours and other contractors
- Controls: the ways each risk is reduced, such as redundant ropes, tool tethering, exclusion zones and weather limits
- Residual risk: what remains after the controls, and who accepts it
- Date, author and reviewer
- Review triggers: what would cause the assessment to be revisited, such as a change in conditions or scope
What a good method statement contains
- Scope of work: what is and is not included
- Personnel: who is on the team, their IRATA levels and who supervises
- Equipment: the ropes, anchors, tools and materials, and their inspection status
- Access and anchors: how the team gets to the roof and where they attach. See anchor point inspection
- Sequence of work: each stage in order, including preparation and clearing up
- Exclusion zones and public protection: what is cordoned off and how. See public safety during façade work
- Rescue arrangements: the plan, the equipment and the people. See rope access rescue plans
- Emergency procedures: who to call and how to reach the site
- Weather limits: when work stops
- Permits, communication and contacts: who signs off, and how the team stays in touch
- Waste and environmental controls: materials, wash water and debris
- Sign-off: a record that each team member has read and understood it
How to review a RAMS
You do not need to be a safety expert to spot a poor RAMS. Ask yourself:
- Does it name my building and describe its actual features, or is it generic?
- Does it identify hazards that are specific to this roof or elevation?
- Is the sequence of work clear enough that you could follow it?
- Does it explain how the public and occupants are protected?
- Is there a site-specific rescue plan?
- Are the people and their qualifications named?
- Is it dated, signed and issued before the work, with a version number?
- Does it say what the contractor needs from you, such as roof access and contacts?
Red flags
| Red flag | Why it matters |
|---|---|
| Another client's name or building on the document | It is a template, not a plan for your job |
| Vague controls such as "take care" or "use appropriate equipment" | It does not describe what will actually be done |
| No rescue arrangements | The plan has a major gap. See rope access rescue plans |
| No named supervisor | Nobody is clearly responsible on site |
| Issued on the day of the work | There is no time for you to review it |
| No review or sign-off | The team may not have read it |
| No mention of asbestos, fragile surfaces or other known hazards | The contractor may not have asked about them |
What the contractor needs from you
A good RAMS depends on accurate information about your building. You will normally be asked for:
- roof and ground access arrangements
- the asbestos register and any other known hazards
- anchor certificates and inspection records
- working-hours and tenant restrictions
- emergency procedures and a named contact
Our site survey checklist covers everything to prepare before the visit.
Where RAMS fits in the whole process
RAMS is one part of a wider picture. A contractor should also be able to show competent, certified technicians, suitable insurance and a proven approach to supervision. See what insurance to ask for and our health and safety and IRATA standards page.
FAQ
Who writes the RAMS?
The contractor, based on the survey and the information you provide. A Level 3 supervisor is usually responsible for it on a rope access job.
Should we approve the RAMS?
You should review it and ask questions. Approval is often a formal part of your contractor procedure, but the contractor remains responsible for the content.
Does every job need a new RAMS?
Each job needs one that is specific to it. A contractor may reuse a structure, but the hazards, controls and rescue arrangements must be checked and updated for each building.
What if conditions change on the day?
The supervisor should stop and reassess. A good RAMS says what triggers a review, such as weather or an unexpected hazard.
Talk to us
Ask us for an example risk assessment and method statement when you request a quote, and we will explain how it works. Read about rope access in London, or request a site survey.
Sources
- The Management of Health and Safety at Work Regulations 1999 (legislation.gov.uk).
- The Work at Height Regulations 2005 (legislation.gov.uk).
- The Construction (Design and Management) Regulations 2015, and HSE guidance on CDM.
- IRATA International, International Code of Practice for Industrial Rope Access (ICOP). Check the current edition.