Quick answer: Weather is the most common reason work at height stops. Wind is the main factor: it makes ropes sway, makes materials and tools harder to control, and can blow things onto the public. Gusts matter more than the average speed, and tall buildings, corners and gaps between buildings can speed the wind up. Heavy rain, ice, snow, lightning and poor visibility also stop work. There is no single universal limit. The risk assessment sets limits for the job, the equipment manufacturer's limits apply, and the Level 3 supervisor makes the call on the day. Plan for lost days, and agree in advance how delays will be handled.
Why wind matters so much
| Effect | Why it matters |
|---|---|
| Rope sway and swing | Makes it harder to control position and increases the risk of being blown into the façade |
| Loss of control of materials | Panels, sheeting, bags and sealant tubes can be pulled or blown away |
| Falling objects | Wind can carry dropped items well beyond the exclusion zone |
| Handling and fatigue | The technician has to work harder to stay in place |
| Equipment limits | Cradles, platforms and cranes have maximum wind speeds |
| Noise and communication | Hard to hear instructions or radios |
See public safety during façade work for how the area below is protected.
Gusts, not just averages
A forecast of a moderate wind can hide stronger gusts, and it is the sudden gust that catches someone off balance. The supervisor will look at both the average speed and the gusts, and at how conditions are changing.
The building makes it worse
Wind at roof level is usually stronger than at ground level, and buildings create their own effects:
- Tall buildings funnel wind down their faces
- Corners often see higher speeds
- Gaps between buildings can create channels
- Open sites and river frontages have less shelter
- Roof edges can have sudden up-currents
This is why ground-level conditions can feel calm while the roof is windy. A good team checks conditions at the roof edge, and often uses a handheld anemometer.
Other weather that stops work
| Condition | Why it stops work |
|---|---|
| Heavy rain | Slippery surfaces, reduced visibility, wet ropes and equipment, and many products cannot be applied |
| Ice and frost | Slippery roofs and ropes, and dangerous falling ice |
| Snow | Hidden hazards and slippery surfaces |
| Lightning | Exposed technicians on ropes and metal structures are at risk |
| Fog and poor visibility | Hard to see the team and the area below |
| Extreme heat | Fatigue, dehydration, and many materials behave differently |
| Extreme cold | Fatigue and equipment issues. Many products cannot be applied |
Who decides?
The Level 3 supervisor is responsible for deciding whether it is safe to start, continue or stop. They work to the limits in the RAMS and the manufacturers' limits for equipment, but they also use judgement. They should have the authority to stop work without pressure from the client or programme. See RAMS explained.
Building managers should not push a team to work in conditions the supervisor considers unsafe. A day lost is far cheaper than an accident.
What happens when work stops
A well-run team will:
- Stop work and bring technicians down safely
- Secure equipment and materials so nothing can blow away
- Make the area safe, for example by protecting open work
- Tell your contact what has happened and why
- Reassess when conditions change
- Reprogramme the work
Weather and materials
Many materials need suitable conditions regardless of safety: sealants, coatings, waterproofing and cleaning products all have limits for temperature, humidity and rain. See façade sealant failure and external repainting for typical requirements.
Planning for weather
| Action | Why it helps |
|---|---|
| Programme in float days, particularly in autumn and winter | Absorbs lost days without chaos |
| Book work in suitable seasons | Reduces delays. See spring exterior maintenance checklist |
| Check forecasts in the days before, and the morning of | Allows a decision before the team travels |
| Agree who decides and how delays are communicated | Avoids disputes |
| Ask for a flexible start date | Lets the team go when the window is right |
| Understand the contract terms on weather | Prevents surprises on cost |
Planning for emergency work is different: see storm damage to a building exterior.
Contract and cost points
Weather can affect programme and cost. It is worth agreeing in advance:
- whether weather days are included in the price or charged separately
- how standing time and remobilisation are handled
- what happens if a window is missed and the work slips to a later season
- how the programme will be updated and communicated
See how rope access is priced for what affects a quote.
Questions to ask a contractor
- What weather limits are set in the RAMS?
- Who decides on the day, and can they stop work without pressure?
- How do you monitor conditions at roof level?
- What is your policy on lightning, ice and rain?
- How are weather delays handled in the price and programme?
- How will you secure the site when work stops?
FAQ
What wind speed stops rope access?
There is no single figure. The limit depends on the equipment, the job, the building and the conditions, and is set in the risk assessment and by the supervisor's judgement.
Can work continue in light rain?
Sometimes, depending on the task and the surfaces. Many tasks, especially sealing and coating, need dry conditions.
Will weather delays cost me more?
It depends on the contract. Ask before you agree.
Can the client insist on working?
No. The supervisor has the authority to stop work, and clients should respect that.
Talk to us
If you are planning work and want to understand how weather could affect the programme, send us the address and your timescales. Read about rope access in London, or request a site survey.
Sources
- The Work at Height Regulations 2005 (legislation.gov.uk).
- IRATA International, International Code of Practice for Industrial Rope Access (ICOP). Check the current edition.
- Met Office forecasts and weather warnings, and equipment manufacturers' operating limits.